Anticipated milestones may shift as work on the project progresses, check back on this post for updates.

COMPLETIONESTIMATEKEY CONSTRUCTION MILESTONES
XApril 2025White Pine pump station groundbreaking, construction begins
XMay 2025Sewer installation work begins, traffic detour on Caughdenoy/Route 31
XJuly 2025Caughdenoy/Route31 traffic flow improvements
August 2025Caughdenoy/Route31 work completed
September 2025Pipeline installation on Verplank/Van Hoesen completed
October 2025Vault/Valve installations on Verplank/Van Hoesen completed
Fall 2025Property restorations on Verplank/Van Hoesen continue through Fall 2025
June 2026White Pine Pump Station site completed mid-2026