Projected Schedule
Anticipated milestones may shift as work on the project progresses, check back on this post for updates.
| COMPLETION | ESTIMATE | KEY CONSTRUCTION MILESTONES |
|---|---|---|
| X | April 2025 | White Pine pump station groundbreaking, construction begins |
| X | May 2025 | Sewer installation work begins, traffic detour on Caughdenoy/Route 31 |
| X | July 2025 | Caughdenoy/Route31 traffic flow improvements |
| August 2025 | Caughdenoy/Route31 work completed | |
| September 2025 | Pipeline installation on Verplank/Van Hoesen completed | |
| October 2025 | Vault/Valve installations on Verplank/Van Hoesen completed | |
| Fall 2025 | Property restorations on Verplank/Van Hoesen continue through Fall 2025 | |
| June 2026 | White Pine Pump Station site completed mid-2026 |