Skip to main content

The Onondaga County Department of Water Environment Protection (WEP) sewer improvement project in Camillus, NY is necessary to rehabilitate a 24-inch pressurized sewage force main that has been in operation for over 40 years. This pipeline conveys wastewater from the Village and Town of Camillus to the Metropolitan Wastewater Treatment Plant on Hiawatha Blvd. Rehabilitation is used to minimize disruptions to homeowners by reducing excavation and construction disturbance. A specialized construction firm will carry out this work using advanced pipeline rehabilitation techniques.


Project Components

The project will use a Cured-in-Place Pipe (CIPP) lining method, a process that strengthens the existing pipe with minimal surface disruption.

• Work will require excavation at two locations (typically at an existing manhole or structure).

• A specialized liner, saturated with a chemical resin, will be inserted into the pipe and inflated.

• The liner will then be heated (or “cured”) to form a durable, new interior pipe within the existing structure.

• Once the process is complete, excavated areas will be backfilled and restored.

During the curing process, steam will be used, which may produce a temporary chemical odor. To minimize any inconvenience, we recommend keeping windows closed during daytime work hours when curing is in progress.


Construction Period

December 2025 through March 2027

Construction Details on Woodmont Drive

Woodmont Drive Section Overview Map

In general, duration of disturbance at any single residence/property should be approximately five (5) weeks from start to completion of surface restoration, mostly in July 2026 to November 2026. Surface restoration generally includes restoring lawns, driveways, and roadways to existing height and condition, including topsoil and seeding for any grass areas disturbed. During this time, our contractor will be actively working on the Project and will provide means of maintaining safe access to roadways and driveways for residents. This project does not require any homeowners reduce their water usage during construction.

This work requires large equipment such as excavators, dump trucks, wheel-loaders, and specialty pipeline equipment. This equipment will be driving on Woodmont Drive to access various locations along the pipeline route, and will be working within a County-owned easement on private property on the properties noted.


Project Milestones

Work on this project began December 2025 and should be complete by March 2027. The contractor’s work hours are generally between 6am and 6pm, unless an unforeseen issue arises. The contractor may elect to extend hours outside of residential areas as needed. We will provide further details on the construction timeline and any additional impacts as the project moves forward.

Project Schedule

Estimated Timing:

Construction Area:

December 2025

Tree clearing behind Woodmont Drive

May – June 2026

Temporary construction matting near Warners Road and Airport Road

May – August 2026

Pipeline work through Reed Webster Park, ending at Warners Road crossing

June 2026

Crossing Warners Road

July 2026

Access road construction between 226 and 228 Woodmont Drive

July – November 2026

Pipeline work from Warners Road through easement, Woodmont Drive neighborhood (see map link)

Oct 2026 – January 2027

Pipeline work from Westside Pump Station through State Fair Property, along railroad tracks

Frequently Asked Questions (FAQs)